Open: Bill of Materials > Records > New Bill of Materials | Details.
Reference and Description are displayed automatically when you select a stock item on the header.
If you are using Manufacturing, this can be reproduced on works orderThe authority to produce a part using the components specified on a BOM and the process specified on the routing. documentation, if required.
The Unit of measure displays the stocked unit of the stock. You cannot change this here.
While the BOM is on hold, you cannot allocate stock or build the BOM.
Note: You can change the status of the BOM by selecting the BOM and clicking Change Status in the toolbar or using the Change Status option on the BOM Records menu.
Note: Click Default to reset the value to the default build quantity value entered in BOM Settings. The value may be modified in line with the unit of measure used.
Note: Click Default to reset the value to the default cost quantity value entered in BOM Settings. The value may be modified in line with the unit of measure used.
Selecting this option posts overhead costs against non materials type cost headings as well as materials type cost headings. Overheads are posted to the Overhead Nominal Account that is specified for each cost Type in Cost Headings in Manufacturing System Manager.
Overhead costs are posted against the finished stock item's Materials cost heading, specified on the Manufacturing tab within the Stock record.
This value is used to calculate markup % during costing. The markup % on the individual component or resource cost heading is ignored.
Note: This is only applicable if you are using Bill of Materials with Manufacturing. If you are using Bill of Materials by itself, you do not need to use this check box.
For example, if you select this box, you will not be able to create a works order using the BOM.
Note: If the BOM is used as a component on another BOM or works order, component priority comes into effect. The setting on the lower level item is ignored when processing the higher level item. You must select Use only in BOM module on the component entry on the higher level BOM.
Leave the option clear if you do not need to know which component items are used in your finished items. You will still be able to trace the components and the finished items.
Note: You cannot select this check box if you have selected a Fixed Quantity serial traceable component on the BOM.
The date Last updated is shown automatically.
Click Image if you want to store a picture of this product.
Note: If you are using all Manufacturing modules, you have selected Perform Compatibility Checks in Manufacturing System Manager system settings Environment tab and you have compatibility issues, the Compatibility Warnings prompt appears.