> Set up Sage 200 / Manufacturing / Enter manufacturing registers / Operations register / Operations settings

Enter operations settings

Note: The View Operations Settings option allows you to view the settings but not amend them.

To enter operations settings

Open: Manufacturing System Manager > Operations Register > Utilities > System Set Up > Operations Settings.

  1. Enter the Resource Steps settings:
  2. To resequence resources in an operation in reference order, rather than by sequence number, select Resequence in Reference Order.
  3. To save changes, click OK.

Go to top