Sage 200 Manufacturing controls each stage of the manufacturing process from planning and materials to tracking orders and collecting payments.
Manufacturing consists of the following modules:
Note: You can use the Bill of Materials module on its own or as part of Manufacturing. If you are not using Manufacturing, you will only be able to use the Bill of Materials module for production.
Sage 200 Manufacturing integrates with the Sage 200 Commercials modules.
BOMA stock assembly and process costing system, which provides facilities to specify the structure of finished items in terms of sub-assemblies and components.s (bill of materials), estimatesForecast project costs, based on expected costs of labour, machinery and operation times. In Manufacturing, estimates are produced for one-off items or non-repetitive batches., sales forecastsThe best estimate of future requirements. This is used as input to the MPS (Master Production Schedule). Forecast orders received should be subtracted from the forecast to leave a residual forecast in the master schedule. Total demands can then be calculated as orders plus residual forecast for each time period., items to make for stock and sales orders are all added to the list of items in demand in the MPSMaster Production Schedule (MPS). The planning of production (usually end item production), to satisfy current and forecast sales orders. The sum of MPS items must equal the agreed sales and operations plan for the items over each planning period. Planning periods are normally a month or a four week period. Items planned within MPS are exploded by MRP (Materials Requirements Planning) to produce the material and capacity requirements. module.
From the Master Production Schedule list a Material Requirements Planning schedule is generated which recommends purchase orders or works orders be created to fulfil the demand. The schedule can be manipulated graphically in Graphical Planner.
You can plan and shift resources, using Graphical Planner. This will help you to deliver the stock you need to fulfil your sales orders.
Graphical Planner does not need to be installed onto every machine that is running Manufacturing, but it must be installed on every machine which will require access to it.
Note: For every machine that requires access, it is necessary to register and activate Graphical Planner individually. Registration is only done online, so a connection from the software to the Internet is required.
Information on installing and registering Graphical Planner is provided in the Sage 200 On Premise Deployment and Installation Guide.
When goods are received they are placed in stock and this allows fulfilment of sales orders.
If you are working in a repetitive batch environment, you can use the Trial Kitting option in Bill of Materials. Trial Kitting checks whether you can build a specified quantity of any BOM. It identifies and displays shortages.
Planning allows you to calculate and display the resources required to satisfy sales orders (Make to Order) and production for stock (Make to Stock). If the materials are not in stock, you can raise purchase orders for them in the Purchase Order Processing module.
The information from the Bill of Materials module feeds into the plan.
Once you have sufficient stock, you can generate works orders to fulfil the BOM. You can generate works orders in the following ways:
From the works order, you can allocate and issue the stock. When the works order is complete, the stock requirements are posted are sent to the Stock Control module. You can then proceed with your sales orders in the Sales Order Processing module.
Note: Purchase orders can be raised in the MRP module.
You may produce one-off jobs. In this situation, the estimate feeds into the plan.
Information for the estimate is drawn from the Stock Control module and from the Labour, Machine and Operations registers. You enter all expected costs for each stage of the job under eight job cost types.
When you turn the estimate into a works order, you can raise purchase orders for the works order in the Purchase Order Processing module.
From the works order, you can allocate and issue the stock. When the works order is complete, the stock is recognised in the Stock Control module. You can then proceed with your sales orders in the Sales Order Processing module.
Other tasks
Generate works orders from a plan
Generate works orders by direct entry
Generate works orders from trial kitting
Converting an estimate into a works order
Reference
MPS (Master Production Schedule)