> Manufacturing / Graphical Planner / Scheduling in Graphical Planner / Perform schedule analysis tasks / Considering resource utilisation

Viewing utilisation of resources

To view resource utilisation

  1. Choose View > Utilization Mode.
  2. This view shows:

  3. Select a resource, and click to see the Utilisation window for the resource.
  4. You can see the: % Working, % Setup Time, % Unavailable, % Idle and % Utilisation.

  5. Click OK.

To print a utilisation report

  1. Choose View > Utilization Mode.
  2. Choose File > Save Utilisation Data.
  3. The Utilisation Data Configuration window appears.

  4. Enter the time period, interval and information that you want to report on.
  5. Click OK.
  6. The data is saved in a format suitable for viewing in Excel.