Entering BOM operation details

Important! If the BOM has been created by converting a one-off works order, an operation is listed in the BOM as a result of the conversion. Do not rename this operation. If you do, you will not be able to update information between the BOM and the Works Order.

Note: As you enter operation details, the total costs by category appear.

  1. In the Operation Record window, enter the same details that you enter in the Operations Register. Note that in the BOM Operation Record window, there is an additional tab: Components.
  2. Note: If you are using Manufacturing, not all the information in the operation entered here or in the Operations Register can be used in Works Order Processing.

  3. On the Components tab, link componentsRaw materials used to manufacture finished goods. from the BOM with the BOM operation by clicking Add.
  4. If you are using Manufacturing, when you create a works orderThe authority to produce a part using the components specified on a BOM and the process specified on the routing. from Trial Kitting, the components are copied to the works order. They can be printed on subcontract operations Work tasks that are subcontracted to external organisations or to other internal departments within the organisation.advice notesA note to a purchaser advising on the intended purchase..

    Note: If the component quantity does not match the unit of measureThe quantity in which a stock item is measured for purchase, sale or storage., the quantity is automatically adjusted to the nearest appropriate value.

  5. To cost the operation, click Cost.
  6. Costs are calculated using base currencyThe operating currency used by your company and the Nominal Ledger; other currencies are regarded as foreign.. If subcontract suppliers use foreign currency, the values are converted to base currency for costing. However, you define the costs in the supplier's currency.

    Note:

    By default, the assumption is that one person performs Manufacturing operations. If you want costing to reflect that more than one person performs the operation, ensure that you select Use manning level in the BOM Settings Costing tab.

    By default, the cost rate stored on the operation is used when costing BOM operations. You can choose always to use the cost rate set on the resource or resource group instead. Or you can choose to use the cost rate on the resource unless it has been overridden on the operation. You make the choice by selecting the Resource Cost Rate Source setting in the BOM Settings Costing tab.

  7. When you have entered all details, click OK.