Open: Planning > Utilities > System Set Up > Planning Settings | General.
Enter the following settings:
Select the number of working days in a week. Planning calculates backwardsThe system works out when you should start work in order to meet the delivery date. from the due date to determine the order start date.
Select the contact role from the drop-down list. This list contains roles defined in the Maintain Contact Roles window.
Select the default setting for viewing tags in MRPMaterials Requirements Planning (MRP). MRP recommends purchase orders, transfers and work orders to balance supply and demand. Recommendation Details and Tags and Exceptions windows.
Select Expanded to view tags set by default as expanded. You can collapse the tags manually.
Select Collapsed to view tags set by default as collapsed. You can expand the tags manually.
This acts as a default for the setting that is displayed in the Make to Stock Item Details window.
Select the check box to ignore any physical stock or inventory policy associated with the stock item. This means that the full quantity entered on the Make to Stock item will be processed by MRPMaterials Requirements Planning (MRP). MRP recommends purchase orders, transfers and work orders to balance supply and demand..
Clear the check box to take into consideration the physical stock and inventory policy associated with the stock item. This means that the quantity entered on the Make to Stock item will be offset against physical stock.