You need to run MRPMaterials Requirements Planning (MRP). MRP recommends purchase orders, transfers and work orders to balance supply and demand. to calculate demands and see make or buy recommendations. MRP processes demands for each product that qualifies in the Master Production ScheduleMaster Production Schedule (MPS). The planning of production (usually end item production), to satisfy current and forecast sales orders. The sum of MPS items must equal the agreed sales and operations plan for the items over each planning period. Planning periods are normally a month or a four week period. Items planned within MPS are exploded by MRP (Materials Requirements Planning) to produce the material and capacity requirements..
An MRP run explodes all manufactured items into component parts. It also calculates the total time needed to manufacture each item or batch and calculates initial start and end dates for each job.
In addition, demands are considered for all products that are below reorder level.
Calculations do not take account of resource capacity. That is the job of the Graphical Planner.
The results of the MRP calculations can be seen:
Current and projected stock levels can be viewed. Action can be taken on recommendations made by the routine.
Note: MRP does not consider alternative stock items in its calculations.
You can view the log file and check the details. You can also send it via email to other users.
Note: If a valid warehouse for obtaining replenishments is not available, this is reported as an error in the log file.
Ensure that you have:
Note: When you run MRP the Apply Replenishment Horizon setting determines whether MRP looks for replenishment from the demand due date or today's date.
Open: Planning > MRP > Processing > Run MRP.
The cut-off date for processing demands defaults to the date entered when demands were last read using MPSMaster Production Schedule (MPS). The planning of production (usually end item production), to satisfy current and forecast sales orders. The sum of MPS items must equal the agreed sales and operations plan for the items over each planning period. Planning periods are normally a month or a four week period. Items planned within MPS are exploded by MRP (Materials Requirements Planning) to produce the material and capacity requirements.. Note: Items with a due date after this date are ignored. |
|
This defaults to the number of days defined on the MRP tab in Planning Settings. It adds a number of working days to the lead time of every works orderThe authority to produce a part using the components specified on a BOM and the process specified on the routing. recommendation. You can change the default, if required. |
|
This defaults to the number of days defined on the MRP tab in Planning Settings. It adds a number of working days to the lead timeThe number of working days elapsing between placing an order for an item and taking delivery. of every purchase order recommendation. You can change the default, if required. |
|
This defaults to the number of days defined on the MRP tab in Planning Settings. It adds a number of calendar days to due dates to find the horizon for replenishments. You can change the default, if required. Note:
Use the Replenishment Horizon (days) box on the Manufacturing tab of Stock Item Details to store the horizon values for individual stock items. The stock item replenishment horizon value overrides replenishment values entered in Manufacturing. |
|
Select the Aggregate Demand check box to group together demand for like products in a product time bucketA time period (for example, a day) in which all demands or requirements are added together and treated as one.. The product time bucket is determined from the Aggregate Demand (days) value set on the Manufacturing tab of Stock Item Details. If you select Aggregate Demand, the method of aggregating demand defaults to the method specified on the MRP tab in Planning Settings. Note: Sales orders which are linked with batch works orders are not included in aggregated demand. |
|
Include demand from |
Choose which items are included. Note: We recommend you include demands from all sources. |
Include replenishments from |
Choose which replenishments are included. Note: We recommend you include replenishments from all sources. |
Ranges |
Choose the product ranges over which MRP is run. Note: We recommend you choose ranges which cover all information. |
What do you want to do?
Reference
MRP Recommendations By Actions workspace
MRP Recommendations By Type workspace