Open: Project Accounting > Utilities > System Setup > Project Accounting Settings | Miscellaneous.
Select from the following settings:
If you use a simple numbering system and want Project Accounting to generate your project codes automatically, select Automatically generate project codes.
Consecutive numbers will be allocated to your projects, beginning with the number entered in the Set next code to box. This will initially be set to 0000000001, but you can change the number if required.
You can change this setting at any time. Any changes will only affect projects created after the setting has been changed.
You cannot change the Set next code to a number that has already been used for a project.
Display project structure when displaying project information
Select this to always display the project structure when displaying a project record (e.g. when amending a project).
Clear this option to hide the project structure in the appropriate windows. You must select Show Project Structure to display the structure.
This can be useful as it enables a user to choose a project item from the project structure, when entering the project analysis on a transaction. If you have projects with different groupings, and many contain the same project items, this can help to make sure that the correct project item is chosen.
Hierarchy separator
Enter your preferred separator. The separator can be in any format up to 10 characters. For example, --, >, or a space.
The separator displays on the ...(by structure) reports and separates each level of the project hierarchy.
Hierarchy Separator | Example |
---|---|
---- | |
4 spaces (pressing the space bar four times). |
|
No separator |
Combine credits and debits on a single document
|
|
Include project information on bill line description
|
Select this to include the project code and description on bill lines in your invoices by default. You can select or clear this option for each individual bill line. Note: This will only apply to bill lines and not comment lines. |
You can post transactions in your project that are not connected to a supplier or customer. These are recorded in the Nominal Ledger.
You can choose whether these are posted as costs or revenues.
Select the As Cost or As Revenue options for Taxable Payments and Taxable Receipts to set the default for these transactions.
Steps in this task
Set up integration for projects
Set up terminology for projects
Time and materials pricing rules