You can change estimatesForecast project costs, based on expected costs of labour, machinery and operation times. In Manufacturing, estimates are produced for one-off items or non-repetitive batches., depending on the estimate status.
You can change:
Note: If you specified password security, you must enter a password to amend an estimate after it has been converted to a works order.
You cannot change:
You can amend Markup (%), Selling Price or Margin (%) values manually on quantity breaks or on stages, depending on your Materials setting in Estimate Settings General tab. If you choose to make manual changes, the order in which you make changes has different effects.
Manually amending the Markup (%), Selling Price or Margin (%) value of any quantity break has the following effects:
Note: Highlighting only applies to the most recent manual change you have made.
The estimate total values are taken from the stage values.
You can manually amend the Markup (%), Selling Price or Margin (%) values on the Totals tab of an estimate stage.
Amending the values on the stage has the following effects:
Note: Highlighting only applies to the most recent manual change you have made.
You can amend the values if you recost the estimate first and choose to discard the amended values.
Amending the values on the stage has the following effect:
Note: Highlighting only applies to the most recent manual change you have made.