There are two ways you can approach building BOMs in Sage 200. You can:
Use the New Allocation option to reserve the stock items that you require to build the BOM. You can undo the allocation if you find you do not need to build the item.
From New Allocation, by clicking OK and Confirm, you can confirm the locations from which stock is allocated, and if you are using traceability, you can select the batch and serial numbers allocated.
Note: You can use the Trial Kitting enquiry before building to test the stock levels required to build. You can access the stock allocation process from Trial Kitting.
Use Confirm Build to build the product from the allocated stock.
The finished stock is updated with accurate quantities for manufactured items.
In this case the stock requirements are transferred directly to the Stock Control module.